Construction Fence Tender Guide

For building owners and project managers: How to create a professional tender for construction fences

Reading time: 10 minutes | Last updated: March 2026
This guide helps you create a professional tender for construction fences with the correct technical terms, service positions, and units.

Service positions

A construction fence tender typically consists of the following services:

Сервіс Опис Typical unit
Deliver Transport to construction site lfm або psch
Set up Assembly of fence system lfm
Retain Provision over rental period lfm/Wo, lfm/Mt або VE
Relocate Moving during construction progress lfm
Видалити Dismantling and transport away lfm

What do these abbreviations mean? See units legend

Важливо: Set up and Retain are separate services - set up is a one-time service, retention is time-dependent.

Position structures in practice

Variant A: Separated

Each service is tendered and priced individually.

Pos. 1.1  Set up         200 lfm
Pos. 1.2  Retain      4.000 lfm/Тиждень
Pos. 1.3  Видалити         200 lfm
          Payment after each service completion
Variant B: Combined

All services in one position.

Pos. 1.1  Deliver, set up, retain, remove
          200 lfm
          Payment: 70% after setup, 30% after removal
Variant C: Hybrid

Base period included, extension separate.

Pos. 001  Base (4 weeks)
          85 lfm
Pos. 002  Extension
          2.380 lfm/Тиждень
          Payment: Base after setup, extension monthly

Units explained

Abbreviation Meaning Calculation
lfm Linear meter Fence length
lfm/Wo Linear meter-weeks Довжина × Тижнів
lfm/Mt Linear meter-months Довжина × Months
VE Billing unit = lfm × Time unit
St Штука For gates, locks, etc.
St/Wo Piece-weeks Кількість × Тижнів
psch Lump sum Fixed price
Linear meters explained

Why linear meters? The term comes from measuring by running along the length - only the length counts, not width or height.

Linear meter (lfm) = the actual fence length, regardless of fence height.

The length is multiplied by the duration:

Example calculation: 100 lfm fence × 8 Тижнів = 800 lfm/Тиждень

This unit price per lfm/week is then multiplied by 800 to get the total retention cost.

Примітка: Calendar days = including weekends and holidays, not just working days.

Technical terms

Fence system
  • Mobile fence / Construction fence Modular system
  • Steel frame elements Galvanized frame
  • Round steel bars Vertical bars
  • Concrete foot / Support foot ca. 25-35 kg
  • Connecting clamp Clamp connection
  • Security clamp Theft-proof
Gates and accessories
  • Pedestrian gate ca. 1 m
  • Vehicle gate / Construction gate ca. 3-6 m
  • Swing gate Opens inward/outward
  • Sliding gate Space-saving
  • Gate lock Chain + combination lock
Безпека дорожнього руху
  • Бар'єр – Red/white barrier (1-2 m)
  • Guide beacon – Warning beacon with reflective film
  • RA1 / RA2 / RA3 – Reflection class (RA3 = strongest)
  • RSA – Guidelines for securing work sites
  • Base plate – Weighted stand base

Legal basis: VOB and construction site regulations

Construction fence tenders in Germany are governed by several legal frameworks. Understanding these is essential for correctly structuring a tender.

VOB Teil C / ATV DIN 18299

The Vergabe- und Vertragsordnung für Bauleistungen (VOB) Part C defines general technical contract conditions for construction services.

Section 4.1 (Nebenleistungen): Construction site setup can be treated as an ancillary service (Nebenleistung) — meaning it does not need to appear explicitly in the tender and is included in the contractor's overhead without separate remuneration.

Alternative: If explicitly listed in the schedule of quantities (Leistungsverzeichnis), it becomes a "Besondere Leistung" and must be priced as a separate item.

Procurement law thresholds

The type of procurement procedure depends on the estimated contract value:

  • Direct award (freihändige Vergabe): up to approx. 3,000 EUR (net) — no formal tender required
  • Restricted tender (beschränkte Ausschreibung): up to approx. 50,000 EUR (net) — selected bidders only
  • Public tender (öffentliche Ausschreibung): above approx. 50,000 EUR — open to all qualified bidders
  • EU threshold (VgV/GWB): above 5,538,000 EUR — EU-wide procurement required

Thresholds are set by UVgO for sub-threshold and GWB/VgV for above-threshold procurements.

Nebenleistung vs. Besondere Leistung: What does it mean for bidders?
Criterion Nebenleistung (ancillary) Besondere Leistung (special)
Listed in LV? Ні Так
Separate remuneration? No — included in overhead Yes — own unit price
Bidder must price separately? Ні Так
Typical for construction fences? Small projects, short duration Medium to large projects
Practical tip: For projects where the construction fence represents a significant cost (typically more than a few hundred euros), always list it explicitly as a Besondere Leistung. This ensures transparency and avoids disputes about what is included in the contractor's overhead.

LABO reference values for construction fence positions

The LABO (Länderausschuss für Bautechnik) publishes reference price data for construction site setup positions. These values are widely used by public clients in Germany as benchmarks for plausibility checks.

Примітка: LABO reference values are statistical averages from submitted bids. Actual market prices in your region may differ significantly — they serve as orientation, not as binding prices.
OZ (Position No.) Service description Одиниця LABO avg.
210.310.021 Construction fence: deliver, set up, remove (one-time) m approx. 6,21 EUR
210.310.022 Construction fence: retain and maintain m approx. 3,02 EUR
210.310.023 Construction fence: retain and maintain m/тиждень approx. 15,36 EUR
210.310.024 Construction fence: remove only m approx. 1,57 EUR
210.310.025 Construction fence: relocate m approx. 2,75 EUR
210.310.052 Construction gate, timber, double-leaf piece approx. 335 EUR

Source: LABO – Leistungsbeschreibung Baustelleneinrichtung (LB-AF 210)

The official position description: "Stahlrohrgitterelement"

In LABO and official tender documents, mobile construction fences are often described as "Stahlrohrgitterelement" or "Bauzaun aus Einzelelementen". These are the terms to look out for when searching tender portals.

Stahlrohrgitterelement
Bauzaun aus Einzelelementen
LB-AF 210 / LB 210

Construction site setup: share of total project costs

The total cost of construction site setup (Baustelleneinrichtung, BE) — of which the construction fence is a key component — typically amounts to the following share of total construction cost:

Project type Incl. equipment holding costs Excl. equipment holding costs
General building construction (Hochbau) 5–8 % 3–6 %
Civil / structural engineering (Ingenieurbau) 6–11 % 3–6 %
Fit-out and finishing trades (Ausbaugewerke) 1–2 %

Source: Bauprofessor (f:data GmbH), Kalkulation Baustelleneinrichtung, 2023

How the BE costs are distributed

When construction site setup is tendered as separate LV positions, costs split roughly as follows:

~65 %
Setup (Einrichten)
~35 %
Clearance (Räumen)

The holding costs (Vorhalten) are often treated as ancillary costs (Nebenleistung) and distributed across the BGK (Baustellengemeinkosten).

Calculation variants according to VOB
Variant 1: Normal positions
BE explicitly listed in LV. Priced like any other position: EKT + BGK + AGK + Wagnis & Gewinn. Not part of the Deckungsbeitrag.
Variant 2: Ancillary service
BE treated as Nebenleistung per ATV DIN 18299. Cost distributed via Zuschlagskalkulation or Endsummenkalkulation across BGK. Part of the Deckungsbeitrag (13–21%).
Variant 3: Mixed
Setup and clearance are listed in LV, holding (Vorhalten) is treated as Nebenleistung. Common in practice for medium-sized projects.

Types of public procurement in Germany

For public clients (municipalities, federal agencies, state governments), the procurement procedure is legally mandated. As a bidder, you need to know which procedure applies to your tender.

Freihändige Vergabe

Direct award

up to ~3,000 EUR

Client selects provider directly, no formal procedure required.

Beschränkte Ausschreibung

Restricted tender

up to ~50,000 EUR

Selected bidders are invited. No public announcement required.

Öffentliche Ausschreibung

Public tender

above ~50,000 EUR

Announced publicly. Any qualified bidder may submit an offer.

EU-weite Ausschreibung

EU-wide tender (VgV/GWB)

above 5,538,000 EUR

Must be published in the Official Journal of the EU (TED). Open to European bidders.

Where to find public tenders for construction fences in Germany

Tip: Search for "Bauzaun", "Stahlrohrgitterelement" or "LB 210" to find relevant tenders.

Ready to respond to a tender? Use our tender generator to create a professional LV-compliant offer text in minutes.

Sample tender

Project: Kindergarten renovation, Musterstadt
Construction time: ca. 32 тижнів
Base period: 4 тижнів
Pos. Сервіс Кількість Одиниця
001 Construction fence deliver, set up, retain 4 weeks, remove 85 lfm
002 Extension retention construction fence 2.380 lfm/Wo
003 Construction fence gate 4m, 2-wing (base period 4 weeks) 1 St
004 Extension gate 28 St/Wo
005 Gate lock (base retention period 4 weeks) 1 Stk
006 Extension gate lock 28 St/Wo
007 Travel cost lump sum 2 Stk
008 Relocate fence elements 15 m
Calculation extension
Project duration:      32 тижнів
Base period:        4 тижнів
Extension:          28 тижнів

85 lfm × 28 тижнів = 2.380 lfm/Wo

Checklist for your tender

  • Total length in linear meters
  • Fence height (standard: 2.00 m)
  • Rental duration (start / end)
  • Number and width of gates
  • Stability (concrete feet or ground anchors)
  • Relocation required? How often?
  • Additional equipment (privacy screen, lighting)
  • Delivery address and access options

Digital data exchange (GAEB)

Tenders are often provided in GAEB format:

Format Purpose
D83 / X83 Tender (Client → Bidder)
D84 / X84 Offer (Bidder → Client)

Current standard: GAEB DA XML 3.3 (since 2019)

Free conversion tools

Official documentation: gaeb.de

Sample tender text

Use these text blocks as a basis for your tender. Adapt the values in [brackets] to your project.

Text block 1: Introduction

tender_text_intro

Text block 2: Main position construction fence

tender_text_fence

Text block 3: Gates

tender_text_gates

Text block 4: Аксесуари (необов'язково)

tender_text_accessories

Text block 5: Безпека дорожнього руху (необов'язково)

tender_text_traffic

Text block 6: Logistics / Delivery

tender_text_logistics

Порада: Use our tender generator below to automatically combine these text blocks based on your requirements.

Tender generator

Configure your requirements below and generate a professional tender text. You can copy it or send it directly to us as an inquiry.
Конфігурація
Project information
Будівельний паркан
Total duration: 8 Тижнів
Аксесуари
Position Кількість Type
pcs
pcs
pcs
pcs
pcs
x
Logistics

Logistics services will be included as separate positions in the tender.

Request tender offer


                                    
Enter your contact details and we will send you the generated tender text with a non-binding offer by email.
Your inquiry has been sent successfully. We will contact you shortly.

Need an offer for your project in NRW?

We deliver and set up construction fences throughout NRW - usually within 24 hours.


JB EventBau

Wittbräucker Str. 115a, 44287 Dortmund

+49 172 2736717 | team@jb-eventbau.de

Related guides

Construction fence calculator

Calculate your requirements and request a quote

To calculator
RSA regulations

Guidelines for barrier fences at work sites

Читати посібник
Безпека дорожнього руху

RSA 21 requirements and equipment

Читати посібник
Regulations and obligations

Legal requirements for construction fences